According to the interface news, staggered electricity usage has been ongoing in Guangdong Province for two weeks. By the end of May, the power rationing situation continued to worsen, the scope expanded, and the time was extended. In some places, factories had already opened three times, stopped four times, which had a negative impact on the factory's order fulfillment. Workers could only be arranged to work in shifts in the morning and evening on days when power could be supplied normally.
A certain enterprise in Zhaoqing stated that it has received an internal notice that power rationing may continue until October of this year, while a street office in Dongguan stated that peak load shifting measures may continue until the end of the year... For manufacturing enterprises, power rationing not only brings them the "dream" of taking a break, but also "nightmares" such as reduced operating rates and extended delivery times.
I dare not accept new orders, old orders are scheduled for July and August
Zhongshan daily quoted a chaozhou power supply bureau staff point of view, according to the current regional load growth than expected, rush hour power supply tension is not enough, even if the overload electricity, "tripping circuit is easy to collapse, causing massive load power outage, so I need some users with peak electricity control".
Energy bureau of guangdong province announced on May 21, due to speed up the economic recovery and sustained high temperature, guangdong power demand continues to grow. To alleviate the tension electricity, guangdong launched a new round of peak power, began around the "stop" six, "open five stop 2" or even "open four stops three" industrial electricity peak.
According to the news of interface, peak power has been in guangdong province for two weeks. At the end of may, electricity situation worse, wider and longer, some local factories have three four, open the performance have a negative impact to the factory orders, the date of the normal power can only be able to arrange workers shift production sooner or later.
Zhaoqing said some enterprise, informed internal power brownouts are likely to continue in the year to October, the dongguan one street agency, said the wrong peak electricity measures or will continue to the end of the year... For manufacturing enterprise, electricity to them, is not only a "dream" of dwell, starts to reduce more, extend the period of delivery, etc. "nightmare".
New single dare not pick up, old orders to July/August
Guangzhou some companies say, haven't met for many years for such a long time and the coverage of such a broad peak electricity consumption. Usual to July through September will have peak power, peak "cut" of the measures, and this year because of the hot weather, the lack of rain, the "electrical power" early for months. The enterprise order has been unable to deliver on time, new orders did not dare to pick up, the old order have been queuing in July and August. Some urgent single customer request by air delivery, so the freight and operating costs are increased.
Zhongshan a number of industrial enterprises informed the electricity blackouts twice a week. A enterprise boss, said a week before a day also don't come out too big effect, but the back into a stop for two days or three days a week. Power failure had a holiday, the worker was inadequate, pay not the goods, but not artificial cost and the rent water and electricity, less pressure. All orders are delayed, not according to the actual delivery of the goods. To compensation for breach of contract to the customer, cause a great loss.
Dongguan said some enterprise, after electricity can only open a machine to single a drive, a lot of single even scheduling is not in right now. Some companies have already staged "empty", larger working days, but there was none to start work the busiest instead is a security patrol. Factory only keep the packaging department sent packing in the yard in the factory, the production department doesn't work. Despite the raw materials have been documented, but you can't boot, owe customer dozens of tons of goods can't delivery on schedule, the boss and staff can only look on. Enterprise has by intelligent production "to" to the era of artificialization, goods elevator can't normal use, employees with pole carrying more than 100 boxes of goods down the stairs.
"Power brownouts to leak caused thousands of companies in guangdong local different degrees of influence, on the one hand is raw material prices, out of stock, on the other hand the outbreak has affected the transport and delivery time. Old order couldn't be delivered on time, new orders can't meet again, want to use diesel generator to solve, but the cost is too high, whether to buy or lease, both to the enterprise the increase of cost in an account.